Timeline

Construction for Transurban Queensland’s $512 million Logan Enhancement Project is now underway. Detailed design commenced n early 2017 and will be completed in late 2017.

Project timeline

Late 2015 Initial concept design released
Late 2016 Queensland Government approved project to proceed
Final concept design released
 Early 2017 Detailed design commenced and early works (including cultural heritage and geotechnical investigations) undertaken
Mid 2017 to 2019 Major construction underway (detailed design continues until late 2017)